Sample 49:   Progress Report

    Wolfe Construction
25 East 40th Street    ·    Beaumont, Texas 77710-6667
409-555-9696    ·    http://www.wlfcst.com
      
   
Date: 3 October 20xx
 
To: Thomas S. Wolfe, President
 
From: Jack Evans, Project Manager
 
Subject: Progress on Hillcrest Apartments for September
 
Pace the reader by summarizing previous progress reports.   Construction on the Hillcrest Apartment Complex began on 17 August and fell behind schedule and fell behind schedule almost immediately because of the heavy rains that month.
     
Summarize the current status.   Current Status

We have not been able to make up time lost in August because of the continuing rain in September. Close supervision and some overtime have prevented us from falling farther behind. We are currently 18 days behind schedule, assuming crew size remains the same and overtime is limited to emergencies only.

      
    The foundation for the entire complex is complete. Framing on the 14 townhouses is complete, and the framers will begin work on the two-bedroom units on Monday, 6 October. The electrical and plumbing subcontractors will also begin work on Monday.
     
Your reader will want to know what to expect. If you anticipate major problems, say so.   Expected Progress

If the weather holds through the rest of this month, I expect to be finished with framing, roofing, and siding by mid-November. That will allow us to begin work on the interiors before the winter rains begin.

     
    One possible problem is the shortage of electricians. Our subcontractor has not been willing to consider providing an additional 5 workers to help us make up for some of the time we have lost because of the rain. Delay on the electrical, will, of course, delay the finish work.
     
    Nevertheless, when we move indoors, we should be able to reduce the total crew by more than 50 percent and begin using the framers and roofers on other projects.



  